ACCORDING
TO CENTRAL BUILDING RESEARCH INSTITUTE
·
BRICK NOS – ( 2.26A + 66.8 ) %
WHERE ,A = PLINTH
AREA OR BUILT UP AREA.
·
CEMENT – (0.153A + 0.57 )TON
1 TON = 10
QUANTAL
= 100 *
10
= 1000
KG
N.A :- 1 BAG CEMENT = 50 KG
·
STEEL --
(21.3A – 314 ) KG
WHERE , A =PLINTH AREA OR BUILT
UP AREA
·
SAND – ( 0.47A – 7 ) Cum.
WHERE A = PLINTH AREA OR BUILT-UP AREA
·
COURSE AGGREGATE – 20 MM (SIZE)
-- (0.176A – 0.21)
WHERE , A = PLINTH AREA ORE BUILT UP AREA
·
MASON – (1.335A + 28 ) DAY + 18% EXTRA FOR
FOUNDATION
MAZDOOR – (4.769A + 32 ) DAY + 25 % EXTRA FOR
FOUNDATION