ANALYSIS
THE RATE OF FOLLOWING ITEMS OF WORKS
BRICK WORK IN CEMENT MORTER ( 1 : 6) :----YOU MAY ASSUME CEMENT – Rs 8100/MT , BRICK Rs 8500/%0NUMBERS ,SAND(coarse)-Rs 1150/M3 , SAND ((med) Rs 950/M3 ,HEAD MASON -326/DAY,ORDINARY MASIN -296/DAY , MAZDOOR-245/DAY.
Consider 10 cum volume of
brickwork.
Size of one brick with mortar =
( 200 * 100 * 100 ) mm3
No
of bricks = 10/(0.2*0.1*0.1) = 5000 nos.
Size
of one brick without mortar =(190*90*90 ) mm3
Volume
of mortar =10 – (5000*0.19*0.09*.009) =2.305m3
Due
to filling and wastage , the quantity is to be increased by 15%
Volume
of the wet mortar =(2.305*1.15) = 2.64m3
When
dry , this quantity to be increased by 33%
Hence
, volume of dry mortar =(2.64*133) =3.51 m3
Volume
of cement =3.51/7 =.50 Cum = 0.72 T
Volume
of sand = 3.51*6/7 =3.0 Cum
Considering 70 % coarse sand & 30% medium sand
Coarse
sand =2.1 Cum
Med.
Sand = 0.9 cum
Particular
|
Quantity
|
Rate(Rs )
|
Amount(Rs)
|
MATERIALS |
|||
bricks
|
5000 nos
|
8500 per 1000
|
42500
|
Sand(coarse)
|
2.1 Cum
|
1150/Cum
|
2414
|
Sand(med.)
|
0.9 Cum
|
950/Cum
|
855
|
Cement
|
0.72 MT
|
8100/MT
|
1500
|
Scaffolding
|
L.S
|
1500
|
|
Total =53102
LABOUR
|
|||
Head Mason
|
½ nos
|
326Rs/day
|
163
|
Mason
|
8 nos
|
296 Rs/day
|
2368
|
Mazdoor
|
17 nos
|
245/day
|
4165
|
Including visti
Total
|
6696
|
||
Contingencies L.S @ ½
%
= 299
Total =60097
Water
charges @ 1% of total = 600.97
Total =60097.97
Profit
& overhead @ 10 % of total = 6069.80
GRAND TOTAL =66767.77